Speak to a world-class expert now.
1-800-FOR-KKAI (1-800-367-5524)
info@kkai.com
PrimeTrack® Instant Conferencing
PrimeTrack® Project Management System (patent pending)


LITIGATION SUPPORT SERVICES


CENTER FOR RAPID RESPONSE ENGINEERING® SOLUTIONS

ENGINEERING AND SCIENTIFIC CONSULTING SERVICES

Project Readiness - CPM Review

Consultant
ZCO is a Mechanical Engineer, Locomotive Reliability and Quality Consultant, Reliability and Maintenance Consultant with world-class expertise in plant operations, maintenance, engineering and reliability management in the refining and chemical industry.

Speak to this experienced, world-class expert now.

For additional or different expertise, browse other top-level expert resumes in Expert Testimony, Failure Analysis, Manufacturing Optimization, KKAI's Center for Rapid Response Engineering® Solutions and a host of other Engineering and Scientific Consulting services.

Learn how KKAI assembles expert teams of any size or skill set combination to meet our clients' needs on a rapid-response basis - no matter how complex the challenge.

Or, peruse our 400 case studies or 500 other expert resumes.


Search Entire Rapid-Response Site
Search Resumes Only
Case Studies

Recently a major oil company requested that an assessment be conducted to determine their readiness to begin a major plant turnaround. A major turnaround contains all the same elements of a major project except that the work is conducted on a 7-day per week, 24-hour per day schedule. As a result, the accuracy of the Critical Path schedule became a focal point of the review.

The critical path or longest continuous string of activities went through the main fractionating column in the plant. The main fractionator is the column that performs the final separation of products before they leave the plant. In order to obtain better "cuts" (reduce losses of higher value products into lower value streams) with reduced energy cost, the number of trays in the column was being dramatically increased.

Several contractors were involved in the work being done in and around the main fractionator. A contractor specializing in tray installation was assigned to perform the tray work. A boilermaker contractor was assigned to install new nozzles that penetrated the vessel walls at new tray locations. And a piping contractor was assigned to run the piping from all the new nozzles to their final destinations.

In preparing the critical path plan, a general contractor was assigned to oversee the assembly of the complete plan. The piping contractor prepared the basic structure of the plan around the order in which piping would be installed. Next came the boilermaker contractor to install tie-ins on vessels. The work of the specialty tray contractor was represented by "dummy" tasks of an assumed duration as "place-holders" while the specialty contractor completed detailed planning.

After all or the individual elements of the plan were installed in the schedule, a duration was calculated using the Primavera program. This duration was advertised throughout the company and used to set up logistics and purchases of supplemental materials during the outage.

It was at this point that the readiness review was requested.

There were two major problems.

First, the "dummy tasks" had never been removed and the internal work sequences never properly connected to predecessors and successors so the critical path duration being calculated was incorrect.

Second, the logic of the order in which nozzles, trays and piping were installed was incorrect. Nozzles needed to be installed first to both set the level for new trays and to serve as the starting point for installing piping. Piping was a close second to the critical path duration and, if piping waited on nozzle installation, would become the critical path.

These finding resulted in several changes. The timing of the boilermaker crew needed to be moved forward. The timing of the specialty tray contractor needed to be moved back. The arrangements for supplementary supplies had to be extended because of the longer outage. By the time the mistake was found, it was already too late to reschedule the large crane that was planned for major lifts to the upper part of the fractionator so some of the lifts were done in a less efficient manner.

Read other articles by this KKAI Associate:

RAM Analysis of a Moderate Sized Chemical Plant

Root Cause Analysis of Hydrogen Compressor Failure

Application of Reliability Block Diagram Analysis to Overall Plant Configuration

Fixing Responsibility for Project Delays Due to Weld Defects

Mapping from Failure to Successful Repair in a High Volume Environment

Mechanical Engineer, Locomotive Reliability and Quality Consultant, Reliability and Maintenance Consultant, plant operations, maintenance, engineering and reliability management in the refining and chemical industry.
Resume of YEU nuclear safety expert consultant
Resume of EJL reliability, maintainability, failure analysis expert consultant
Resume of GEF value analysis, value engineering, expert consultant
Resume of CYV chemical, operations, process, manufacturing expert consultant

To search for specific expertise, enter your search query (type of expertise you are seeking) in the box below, choose to search the entire Rapid-Response site or just resumes and brochures, then click the search button. Please note that the list of resumes available online is a select subset of our vast database. If your search of our site does not reveal the expertise you are seeking, please call us toll-free (in the U.S.) at 1-800-367-5524 or contact us for more information and we will gladly assist you in locating the specific expertise you require.


Search Entire Rapid-Response Site
Search Resumes Only
Case Studies


Have an urgent litigation support or engineering and scientific consulting need? Contact KKAI now for world-class, expert rapid response.

1-800-FOR-KKAI (1-800-367-5524)
info@kkai.com

BACK TO THE TOP OF THIS PAGE
Kevin Kennedy & Associates, Inc.
Rapid Response Engineering® Solutions
3905 Vincennes Road, Suite 320
Indianapolis, Indiana 46268
(317) 536-7000 voice
(317) 536-7220 fax

SEARCH our site

Search Entire Site
Resumes Only
Case Studies

Our innovative, proprietary and patent-pending PrimeTrack® Rapid Response capabilities can help you quickly find the experts you are looking for.

Search here to examine any of the more than 500 resumes for KKAI lead consultants and associated experts from our global organization.

Simply enter the type of expertise you seek, and then choose to search the entire Rapid Response site, to just read resumes only, or to read any of KKAI's more than 400 case studies. A rapidly growing organization, KKAI adds more than 20 expert resumes and 40 expert case studies to its Web site each month, so check back often.


CALL US TODAY
Call KKAI with an urgent need. Experts are paged instantaneously and can be made available in a virtual conference room. To experience this unique capability, please call us at 1-800-FOR-KKAI (1-800-367-5524) from the United States or 317-536-7000 if calling internationally.